Dear Client,
As part of our ongoing commitment to ensuring the security of your online trading experience, we would like to inform you of our protocol for addressing any suspicious activities observed on your trading account
Should you notice any irregularities or suspect unauthorized access to your account, we kindly request that you take immediate action by following the steps outlined below:
Send an Email Please send an email to stoptrade@acml.in from your registered email ID. In the email, briefly outline the suspicious activity you have observed.
Phone Call Alternatively, you can call us at 07965081981 Ext: 4 from your registered mobile number. This will enable us to address your concerns promptly.
When contacting us, please ensure you provide the following details:
By providing this information, you enable us to swiftly investigate and take appropriate measures to safeguard your account.
Your security and peace of mind are of utmost importance to us, and we appreciate your cooperation in maintaining the integrity of your trading account.
The project involves construction of a 400kV (Quad) double-circuit transmission line under the TL-01 package of the Bellary'Davanagere 2nd 400kV line scheme. It is part of a renewable energy evacuation system aimed at integrating 0.25 GW at Davanagere and 2.75 GW at Bellary into the national grid, with a line length of around 70 km connecting the Bellary Substation to the Davanagere Substation.
Bajel Projects said the project will be executed within 21 months from the date of issuance of the notification of award. The contract is a domestic EPC order, and the company confirmed that neither the promoter, promoter group, nor group companies have any interest in the awarding entity.
Meanwhile, the company has also secured a major order for the 765kV AIS Substation Package from Maharashtra under Power Grid Corporation of India (PGCIL) through its SPV, NES Pune East New Transmission. The project involves the construction of a new 765kV AIS substation at Pune East, along with bay extension works at Karjat and Lonikand-II substations. The project is scheduled to be executed within 21 months from the date of issuance of the Notification of Award.
Bajel Projects (BPL) is a leading company in the business of power infrastructure, with a strong presence in the power transmission and power distribution sectors. BPL was formerly part of Bajaj Electricals under the EPC segment.
The company reported a consolidated net loss of Rs 0.42 crore in Q3 FY26, compared with a net profit of Rs 1.46 crore posted in Q3 FY25. Revenue from operations declined 9.64% year-on-year to Rs 562.34 crore in the quarter ended 31 December 2025.